In-stream projects 1973 - 1989
The first in-stream project was accomplished the first
year the Chapter organized, 1973. For the regular September meeting, members
met on upper Spring Creek under President Joe Humphreys' leadership. The
group repaired several jack dams and replaced some bank cribbing in the
Neidigh quarry area and later had a picnic lunch at the Humphrey's place.
Several years later, similar work was done in the
quarry area. A group from the National Guard Unit on Fox Hollow Road
assisted with manpower and trucks to help move the heavy timbers and rocks
in building jack dams and stream cribbing. Those first projects were done
with little involvement of the Fish Commission.
A more involved project of installing a large mud sill
at the lower end of Neidigh's quarry area was organized by Dan Shields in
1981and 1982.The project was designed by the Fish Commission. Many large
telephone poles and mcire than 30 tons of rock were used in building the
sill. The structure is doing an excellent job of controlling stream bank
erosion and providing a sanctuary for wild trout. In addition, Dan Shields
and a few members did some riprap work in Spring Creek Park near Houserville
during the 1980s.
In a 1989letter, addressed to Penn State's College of
Agriculture, the board expressed its concern about the severe bank erosion
and resulting stream siltation caused by cattle and other livestock on the
University farms just downstream of the confluence of Slab Cabin Creek and
Spring Creek near Houserville. Originally drafted by Bob Carline and his
stream improvement committee, the letter requested that some form of fencing
be constructed along Spring Creek to keep livestock from entering the
stream. The welcome response from the College was that they would indeed
fence Spring Creek where it crossed University pasture lands as a first step
in resolving the siltation problem.
About this time the Chapter helped organize and joined
the "Spring Creek Coalition", a consortium of organizations concerned with
the preservation of and enhancement of the Spring Creek watershed. The
Coalition decided to "adopt" Spring Creek as part of the Pennsylvania Fish
Commission's Adopt-a-Stream Pro gram. Also at this time, the Chapter
received $35,000 from the Borough of Bellefonte (as part of a settlement
made by the Borough for delay in expanding its sewage treatment plant). In
1990 the Environmental Protection Agency gave the Chapter permission to use
much of this money for stream bank stabilization projects.
The upshot of all this is that, with the cooperation of
the University, the Coalition, private landowners, a local limestone quarry
(which has supplied many tons of rock), and the Fish Commission, the Chapter
is currently involved in a comprehensive effort to effectively reduce
siltation of Spring Creek where it flows through both public and private
lands. This past spring and early summer many tons of rock were hauled to
University pasture lands and used to construct mud sills which protect
exposed banks from erosion. Chapter members and the University fenced the
pasture lands abutting the creek and planted trees to provide shade. Under
the direction of chapter member Mark Ralston, stream improvement work
continues at Bellefonte's Talleyrand Park and on a farm property below
Houserville. Additional fencing and streambank stabilization projects are
planned for the Slab Cabin and Cedar Run tributaries of Spring Creek.
Tree Planting
Tree and shrub planting along Spring Creek have been
done over the years. The first effort was headed up by Joe Spino in 1974.An
unknown number of black alders were planted in Neidigh's meadow below the
quarry. These have grown very well and some are now almost a foot in
diameter; also, they are now reseeding themselves in kind. These trees
protect against stream bank erosion in places and are providing a cooling
effect.
Another concerted effort, directed by Dan Shields, was
made over a three- year period
starting in 1980.
During that time several hundred trees were secured
from the Fish Commission. Dan divided them into small packets of up to 50
trees each and gave them to interested members who planted them along the
stream where they normally fished. In 1982 Dan, Elton Tait and Ev Shafer
planted a large number below the Route 550 bridge near the Borough of
Bellefonte. Many of these trees, mostly dogwoods and willows, survive today.
Easement - Bellefonte Rail Road Easement
During 1990, chapter member Eugene Proch informed the
board that an easement for a section of lower Spring Creek was possible from
Bellefonte CEDA-COG joint Rail Authority. Negotiations by chapter members
Jim Strauss and Mark Faulkner enabled an agreement to be signed between the
chapter and the Rail Authority on February 11, 1991. The easement for
approximately 1/3 mile of streambank includes the section of Spring Creek
from the confluence of Buffalo Run downstream to the Spring-Benner-Walker
Sewage Treatment Facility.
Easement – Houserville
In 1985 the Chapter purchased a three-quarter acre
parcel of land along Spring Creek just below the intersection of Houserville
Road and Benner Pike. The Chapter paid $3,400 for the land. The main purpose
for this acquisition was to demonstrate to other landowners that Trout
Unlimited also has a vital stake in the future of our name sake stream. At
this writing, our Spring Creek property has been sold in exchange for the
original purchase price and more extensive easement privileges along
properties between the Route 26 Bridge and Houserville Park